Assess the CertsIQ’s updated 1D0-1057-24-D exam questions for free online practice of your Oracle Project Management Cloud 2024 Implementation Professional - Delta test. Our 1D0 1057 Delta dumps questions will enhance your chances of passing the Oracle Project Management Cloud certification exam with higher marks.

Exam Code: 1D0-1057-24-D
Exam Questions: 132
Oracle Project Management Cloud 2024 Implementation Professional - Delta
Updated: 02 Jun, 2025
Question 1

When scheduling the Update Project Performance Data process to run on a periodic basis, which
summarization method would you select? (Choose the best answer.)

Options :
Answer: C

Question 2

As part of maintaining (importing new employees that were added last week) project enterprise labor resources
in your organization, you submit the Maintain Project Enterprise Labor Resources process to create and update
resources based on changes In HCM. You define maintenance conditions on the Manage Project Enterprise
Labor Resource page to process both employees and contingent workers.
Which three are parameters that are based on which the system identifies the new resources?

Options :
Answer: A,C,D

Question 3

Your customer started operations and all projects in January 2015. They implemented Enterprise Project

Structure for calculating project labor demand by using the Annual option. When they view the labor demand
on 15-Dec-2015, the project hierarchy viewer shows data only for the year 2015. The client expected the
demand to be shown for a year, from 15-Dec-2015 to 15-Dec-2016.
Identify how the project hierarchy viewer displays labor demand information. (Choose the best answer.)

Options :
Answer: B

Question 4

Your customer has a requirement to allow adjustment and reversals for transactions imported from an external expense entry system. Which section on the Manage Project Transaction Sources page will allow you to enable these options?

Options :
Answer: B

Question 5

Your customer wants to automatically allocate unassigned asset lines and common costs across multiple assets
based on the construction-in-process cost of each asset. Identify the asset allocation method that you must
use as the default method while configuring project types to meet this requirement. (Choose the best answer.)

Options :
Answer: C

Viewing Page : 1 - 14
Practicing : 1 - 5 of 132 Questions