Assess the CertsIQ’s updated 1D0-1057-25-D exam questions for free online practice of your Oracle Project Management Cloud 2025 Implementation Professional - Delta test. Our 1D0-1057 Delta dumps questions will enhance your chances of passing the Oracle Project Management Cloud certification exam with higher marks.

Exam Code: 1D0-1057-25-D
Exam Questions: 132
Oracle Project Management Cloud 2025 Implementation Professional - Delta
Updated: 16 Apr, 2026
Question 1

As you go through the first-quarter close for your customer, you notice that the burden amounts calculated do
not seem to be right. Based on the calculations, you notice that the amounts calculated are not considering the
burden schedule override at a task level, which was done during the second month of the quarter. Identify the
reason for this problem. (Choose the best answer.)

Options :
Answer: B

Question 2

Your customer wants a project start date to cascade to the project tasks but does not want the finish date to be
cascaded. Identify the default setup in a project template that can be used to enable this. (Choose the best
answer.)

Options :
Answer: A

Question 3

Your organization has been awarded a new contract based on which you are allowed to sell:
Items not tracked in inventory
Inventory items
Services
Which contract structure would fulfill your requirement of item sales? (Choose the best answer.)

Options :
Answer: B

Question 4

Which application generates external roles to grant both function and data security? (Choose the best answer
.)

Options :
Answer: B

Question 5

Your customer has the following setups on the project plan type that they are using for their projects:
Use Task Planned Dates as Task Assignment Dates = Yes
Automatically Roll Up Task Planned Dates = Yes
Synchronize Task Transaction Dates with Planned Dates = No
With these setups in place, you perform the following actions:
1. Create a new subtask (Sub Task 1) with a start date of 15-Jun-2016 on the project that has as start date of
01-Jul-2016.
2. Create another new subtask (Sub Task 2) after the previous action is saved.
What would the correct behavior of the application be after these actions? (Choose the best answer.)

Options :
Answer: C