Assess the CertsIQ’s updated CTAL-TTA_2019 exam questions for free online practice of your ISTQB - Certified Tester Advanced Level - Technical Test Analyst (2019 Syllabus) test. Our CTAL TTA 2019 dumps questions will enhance your chances of passing the ISTQB Certified Tester Foundation Level certification exam with higher marks.
Subject to testing is a software system (COTS) for Project Administration and Control (PACS). PACS is a
multi-project system for controlling the project time, e.g., in terms of scheduling and tracking, and managing
the productivity of projects, e.g., in terms of effort and deliverables.
During various interviews with stakeholders the following information was gathered:
• Using PACS is not business critical. There is no impact such as high financial losses or problems to the
operational continuity of an organization. Its application is not critical since the software package does not
support directly the operational, or the primary, business processes of an organization. It supports (project)
management in the project planning and tracking process. Of course, it will be highly annoying for users if the
system “goes down” from time to time. Although this does not have a high impact for the business process as a
whole, the Mean Time Between Failures (MTBF) still needs to be at a good level to be successful in the
market.
• Users of PACS typically have an academic educational level, but have no prior experience with this
particular type of project management software. The system will be used by a large number of users within an
organization.
• The system will be used on a regular basis, e.g., several times per day by project managers and several times
per week by project employees. This means that the system will not be used very intensively, often only for
some data input or an information request. Its usage is not considered to be very time-critical.
• The data is recorded on-line and real-time. The system is expected to run in multiple hardware environments
in various network environments. It is also expected that changes in the operational environments will happen
in the upcoming period that also need to be supported.
Based on the information provided by the stakeholder, which combination of non-functional quality
characteristics should you propose to test as part of your test approach?
Which option describes a good practice when applying test automation for a Regression-averse test approach?
SELECT ONE OPTION
Which specification-based technique could be used to enhance coverage for this code fragment?