A summary WBS is usually developed in the
A _____ estimate prepared from layouts, sketches and flowsheets, should be accurate within (-10, +25%).
Your company has asked you to be the project manager for the product introduction of its new DeskTop Rock media system. You recently published the project scope statement. Which of the following is not contained in the project scope statement?
Which of the following is a tool and technique for activity duration estimating?
Which is an input to the Collect Requirements process?