Assess the CertsIQ’s updated PRINCE2-7-Practitioner exam questions for free online practice of your PRINCE2 7 Practitioner (7th Edition) Project Management test. Our PRINCE2 7 Practitioner dumps questions will enhance your chances of passing the PRINCE2 Project Management certification exam with higher marks.

Exam Code: PRINCE2-7-Practitioner
Exam Questions: 53
PRINCE2 7 Practitioner (7th Edition) Project Management
Updated: 25 Aug, 2025
Question 1

Discrimination against marginalized groups, in particular the homeless and refugees, is growing at a concerning rate.

Under which heading of the change management approach should this information be recorded?

Options :
Answer: A

Question 2

The Contracted Project Manager is drafting the quality management approach during stage 1. The Director of Campaigns has suggested that the objective of project quality management should be to ensure that the project team is familiar with, and able to use, a variety of media (tv, press, and social networks) by the end of the project.

Is this an appropriate application of the ‘quality’ practice, and why?

Options :
Answer: C

Question 3

Here is an item of information relating to the 'quality' practice.

Under which heading of the quality management approach (A-E) should they be recorded?

Options :
Answer: C

Question 4

The project team has received some great news. They have received a large anonymous donation. As a result, they have decided to extend the scope of the project. It has been agreed that they should now hold some workshops and actively visit large corporate organizations to do presentations and distribute merchandise to enable publicity. The project team believes that this will increase awareness of discrimination significantly.

Here is an action. Which role (A - E) should be responsible for each action?

Options :
Answer: E

Question 5

The project is in the 'managing a stage boundary' process during stage 3 and there has been a significant delay in the implementation of the social media campaign. As a result, the time and cost tolerances for the stage are forecast to be exceeded. The project manager has reported the situation to the project board and they have requested that the project manager replan the stage, allowing extra time and cost. In addition, the project board wants to know how the TV and press campaigns are progressing and what is left to do on the social media campaign.

In the 'managing a stage boundary' process, which role should be responsible for providing this information about the campaigns to the project board?

Options :
Answer: A