If Project tolerances were threatened, who needs to be notified?
Which of the following statements is TRUE with regard to expected benefits?
ABC Company has set an overall budget for the Health and Safety Training Project. During stage 3, there was a delay in delivering the 'e-learning course' by the external consultancy and the cost and time tolerance for the work package was exceeded. This led to additional costs in running the 'planned pilot courses'. Therefore, the project cost will exceed the agreed overall project budget, so the project board requested additional funding from ABC Company’s board of directors. Is this an appropriate action, and why?
A work package has been authorized by the project manager for the 'classroom-based training materials' and
the 'accredited classroom-based course'. The course developer (team manager) has provided an exception
report to the Senior Supplier stating that the time tolerance for the work package will be exceeded and this will
cause the stage 2 plan to go into exception. The Senior Supplier has instructed the course developer to
produce an exception plan.
Is this an appropriate application of the 'controlling a stage process', and why?