The executive identified that there would be a benefit to the construction companies as their working time lost due to accidents would be reduced. This was included as a benefit to ABC Company in the business case for the Health and Safety Training Project. Is this appropriate, and why?
While planning the initiation stage, the Project Manager reviewed some threats that had been recorded in the Daily Log. Which threat should have been assessed for possible risk responses to be included in the Initiation Stage Plan?
The work package to produce the 'updated corporate quality procedures' was created during stage 3. Before accepting the work package, the team manager produces the team plan and finds that the expected delivery date is unrealistic. As a result, the project manager agrees an extra two weeks to complete the work package, within the current stage tolerance. The work package is then accepted by the team manager. Is this an appropriate application of the 'manage product delivery' process, and why?
As part of the 'authorize a work package' activity, the project manager is preparing the work package for the marketing materials. The project manager has asked the team manager for this work package to draft some specialist sections of the work package. The project manager and project assurance will review these sections before the work package is authorized. Is this an appropriate action, and why?
Which statement applies to the Records section?